Cooling, Heating, and Power for Buildings
Home> Tech Professionals> Design Tips> Site Requirements
 
News and Events
General Public
Technical Professionals
Basics  
Benefits  
Technology Status  
Installations  
Assessments  
Equipment Guide  
Application Manual  
Design Tips  
Market Potential  
Emissions  
Project Financing  
Expert Contacts  
 

Building Owners
Policy Makers/Planners
Financial Institutions
Market Sectors
Solicitations
Library
Relevant Links
DOE Staff
Contact Us
Site Map
 
search
 

Design Tips - Building and Site Requirements

This section describes the requirements involved in interfacing modular integrated energy systems (IES) with conventional building systems. This document is not intended to be a design guide for these building and site interfaces (which is the responsibility of the cognizant design engineer who is applying a Reference Design to a particular building). The Reference Designs are based on 2MW to 5MW Solar gas/diesel turbine generators, heat recovery boiler(s) with duct firing, and Broad USA heater/chiller(s) serving a variety of load scenarios and generic facilities. As such, the focus of this document is on identifying the kinds of conventional systems that are compatible with the Reference Designs, and provides a list of design resources that practitioners can use in applying modular IES technology. An illustration of key building interfaces is shown below. Additional discussion is presented in each section.

Utility Loads Siting Codes and Standards Waste Mechanical Electrical Instrumentation


Background

Introduction

The information presented here is the results of technical work being performed for developing packaged system designs for large (2 to 5 MW) building cooling, heating, and power (BCHP) Systems, also known as Integrated Energy Systems (IES). This work is funded by the U.S. Department of Energy and is being administered by Oak Ridge National Laboratory (ORNL Subcontract 4000011476). Honeywell and its team members, Broad USA, I.C. Thomasson, and the Chelsea Group, are developing a set of CAD-based packaged IES system designs and a supervisory control and optimization capability for these systems. This section covers the work performed under Task 2.1: Building & Site Requirements.

Project Overview

The objective of the program that developed the information in this section was to develop large (2 to 5 MW) BCHP packaging technologies and field-test a prototype system. These technologies include a set of “reference” CAD designs and an optimizing supervisory control system. Installation scenarios for these systems can vary widely, so packaging is dependent on modularity, namely, the ability to construct a system by choosing from a selection of compatible components with standardized interfaces. This is especially important for larger BCHP systems, where the physical size of the equipment prohibits the manufacture and shipment of the entire system in one enclosure. Packaging in this way still simplifies the design and installation process by reducing the amount of site-specific engineering and site preparation required.

This project was focused on BCHP packaged systems in the 2- to 5-MW size range, with 500 to 2000 tons of cooling, intended for central plant and district energy applications serving multiple buildings. The major modules are a turbine-generator, a heat recovery steam generator, and an absorption chiller. The set of “reference” packaged designs to be developed will allow these modules to be applied to a variety of customer sites.

Back To Top
 

Codes and Standards

The purpose of this section is to provide the reader with a overview of the codes and standards that will generally apply to a CHP plant. By no means is this list comprehensive.

1.
Building Codes
 
International Building Code (IBC), developed as a model code for model code organizations:BOCA, UBC, SBC
State & local codes
 2. Mechanical Codes & Standards 
   2.1  ANSI Standards
   
Flanges and piping B16.5, B16.1, B16.47, etc.
 
2.2
ASHRAE Standards
   
Guideline 1-1996 The HVAC Commissioning Process
Std 15-2001 Safety Standard for Refrigeration Systems
Std 62-2001 Ventilation for Acceptable Indoor Air Quality
Std 114-1986 Energy Management Control Systems Instrumentation
Std 135-2001 BACnet - A Data Communication Protocol for Building Automation and Control Networks
Std 147-2002 Reducing the Release of Halogenated Refrigerants from Refrigerating and Air-Conditioning Equipment and Systems
   2.3  ASME Standards
   
Boiler Power Piping 31.1
Chemical Process Piping 31.3
Boiler and Pressure Vessel Code
Pipe Flanges and Flange Fittings B16.5
  2.4 ASTM Standards
    These are generally equipment standards and pertain to individual components of the CHP system
  2.5  UL Standards
  2.6  State & Local Code 
    A number of large municipalities (Chicago, New York City) maintain their own codes
 3. Electrical Codes & Standards
  3.1 IEEE
   
Interconnection Standard 1547
DG Standard 1589
IEEE Standards 519-1992, 929-2000, 84 (Harmonic Limits and Voltage Fluctuations, Waveform)
  3.2 National Electric Code (NEC)
  3.3 ASTM Standards
    These are generally equipment standards and pertain to individual components of the CHP system
  3.4 UL Standards
  3.5  State & Local Codes
    A number of large municipalities (Chicago, New York City) maintain their own codes
  3.6 State & Local Codes
 4. National Fire Protection Agency (NFPA) Codes
 
Gas-Fired Equipment Code 8501
Oil/Diesel-Fired Eqipment Code 31
National Gas Fuel Code (NFPA 54)
Liquid Fuel Storage Tanks Code (NFPA 30)

Back To Top
 

Electrical Interconnections

The electrical equipment of the CHP facility, though not the most expensive part of the construction, is vital in the operating success of the facility, and is probably the most complicated and diverse part of the design. In most facilities there are two major areas of focus, the utility interface point and the CHP construction itself. We will consider these two points as separate parts of the design and in many cases may be remote from each other by a substantial distance.
1.
Utility Interface Point
 

The interface point is usually located close to or within the distribution substation for the facility. The following upgrades are usually considered in the design of this point of intersection. 

2.
Low-Med Voltage/Station Power Capacity
 
The CHP facility consumes power itself to operate. Although supplied by the CHP equipment itself through transformers, often an additional feed is used to provide this power from the utility during startup. A new standby generator may also be used.
3.
High Voltage-Substation
 
The CHP plant connects to the grid at the substation; sufficient space must be present for the switchgear and transformers required.
 
3.1
Over / Under Voltage Protection
 
 
It is usually critical for the cogeneration facility. The utility normal mode of design is to avoid voltage drop so they operate their distribution system at a higher than nominal level so that nominal levels can be maintained on the extended reaches of the distribution system. Cogeneration equipment removes load or may even export power removing voltage drop or creating voltage rise thereby driving the site into higher than normal voltage levels. Some utilities take an unrealistic, bureaucratic approach with mandatory trip requirements while operating at very high voltage levels. To avoid nuisance tripping of the interface breaker a fast acting, over voltage relay (ANSI Device 59) is required.
 
 3.2
Under Voltage Relaying
 
 
Under voltage relaying (ANSI Device 27) also required is usually not as critical as over voltage control.
 
 3.3
Out of Frequency - Over/Under Frequency Protection 
 
 
Out of frequency / over/under frequency protection (ANSI Device 81 O/U) is also important. The first signs of system instability occur in the system operating frequency. For a cogeneration plant operating in parallel the frequency is set by the utility. The system frequency protection should be set outside the utility trip points and set for on site equipment protection only. In the unlikely event of utility grid instability the cogeneration equipment should stay on line to avoid placing the facility load on a utility tending toward instability. Utility guidelines may be obtained to assist in making these determinations.
 
 3.4
Out of Step Protection
 
 
Normally any breaker interfacing between the utility and the cogeneration must be equipped with a Sync-check relay, (ANSI Device 25). This relay will be capable of monitoring the voltage via potential transformers (PT) on the line and load side of the device. The protective relay will prevent closing the breaker unless the voltages levels are the same and the both systems are in phase. If the co generation plant were accidentally connected to the utility out of phase, the two systems would attempt to instantly align themselves with other. This would cause major stress on the mechanical and electrical equipment operating on the site. 
 
 3.5
Reverse Power Protection
 
 
Reverse power protection may be required on facilities, which have not negotiated a power sell agreement with the utility. The reverse power relay (ANSI Device 32) monitors the direction of power flow and will, after a time delay, initiate a trip when power flows from the site to the utility grid. There is an option to either trip the site-interconnecting breaker or trip the generating equipment causing the reverse power. It is usually less disruptive to trip the generating equipment and suffering the impact of the increased power use penalties from the utility than to take the entire site off line. This however is not always the case, and must be analyzed for each site.
 
3.6
Detecting Unintentional Island Operation
 
 
The condition of unintentional island operation may occur when the facility load is approximately equal to the output of the cogeneration equipment. Under this condition, if a utility breaker upstream opens it may be difficult for the relaying at the interface point to detect that the utility is no longer connected. As long as the load is closely matched to the generators output the facility will continue to operate until a load change pushed the generator voltage or frequency out of the protection zone provided by the interconnecting relaying. Under this condition the facility may remain energized for several minutes creating the possibility of the upstream breaker reclosing on the facility out of phase or a possibly unsafe condition for utility maintenance workers. This condition does not occur during a fault since the fault energy would pull the generation equipment down, taking the CHP off line.
 
3.7
Power Import / Export Power Control
 
 
One feature that becomes vital in cogeneration facilities is the use of feed back control to limit the amount of power purchased from the utility. This is accomplished by sending a signal from the utility interface breaker to the CHP. Based on this feed back signal the turbine controls continually adjust the governor to maintain a fixed amount of power flowing through the utility interconnect breaker. This is modified only by the limits of the CHP generator.
 
3.8
Reactive Power Import / Export Power Control
 
 
A similar control function may be accomplished by monitoring the amount of reactive power purchased from the utility. The feed back signal from the interface breaker to the CHP allows the voltage regulator to be continuously adjusted to maintain a constant power factor across the utility main breaker. Protective features must be supplied for the generator controls to prevent over exciting the generator. The additional cost for this control feature may be recovered from utility charges against reactive power purchases.
4.
The CHP Electrical Design Considerations
 
4.1
Distribution System Configuration
 
 
The first consideration for a new CHP is the configuration of the distribution system to which it is connected. The presence or absence of a neutral in the distribution system will determine how the cogeneration equipment is connected to the system. Another consideration is to whether the system will be operated as an island or not. The presence of a neutral indicated that transformers are connected wye on the primary side. If this is the case an Isolating transformer will be required since the generator is not a good source for generating neutral currents.
 
4.2
The Isolating Transformer
 
 
The isolating transformer for the CHP cogeneration equipment allows an exact match between the site distribution and the generator output. It also provides a level of isolation between the generator and exposed distribution. Typically the wye connection faces the distribution system to supply ground faults and neutral currents, and the delta faces the generators to provide isolation. The generator is typically connected wye and grounded through a reactor or resistor that establishes the ground reference on the generator side.
 
4.3
Generator Bus
 
 
The generator can operate on an electrically isolated bus or can supply auxiliary CHP loads. If the generator bus is used to supply other loads a grounding bank to establish the generator bus ground reference must be installed for those situations when the CHP auxiliary loads are operating and the turbine generator is not in operation.
 
4.4
Underground Distribution System
 
 
If the cogeneration equipment is connected to an underground distribution system, not exposed to lightning flash over events, and the system has no neutral the turbine generator can be connected to the distribution system without an isolating transformer. When this is the design care must be taken to properly ground the generator or specify the proper generator construction to avoid harmonic currents circulating between the distribution system and the utility distribution system. The pitch of the generator windings must match those of the utility system, typically 2/3. This type of construction is more expensive for this size alternator. Another option is to purchase a standard alternator and mitigate the harmonic currents that can result by increasing the impedance in the generator neutral connection. This should be carefully considered since the installation can impact the performance of lightning arresters in the distribution system.
 
4.5
Synchronizing Switchgear Requirements
 
 
4.5.1 Synchronizing Switchgear
 
 
  Synchronizing switchgear is a piece of electrical switchgear constructed in such a manner to interface the generation equipment to the electrical distribution system. This gear contains the synchronizing breaker and all of the protective relaying required for protecting the alternator from electrical disturbances that occur on the distribution system. The location of this equipment in the electrical configuration for the CHP is between the generator and the first distribution bus upstream. In some cases the isolating transformer cam be placed between the synchronizing breaker and the alternator.
 
 
4.5.2 Synchronizing
 
 
  Synchronizing is the operation of adjusting the generator voltage to match the line voltage, aligning the generator phase angle to match the utility and closing the synchronizing breaker. The turbine control equipment performs this operation automatically. Provision is also provided for manual override in the event that the automatic system fails. The manual system consist of volt meters with selection for line and generator voltage comparison; sync-scope for monitoring each system phase relationship; sync-lights which are not illuminated when the two systems are in phase; manual voltage and speed switches, raise and lower; and a manual switch to close the synchronizing breaker.
 
 
4.5.3 Protective Relaying
 
 
  Protective relaying for the typical generator protection package may consist of the following. Presently many of these functions are housed in a multifunction, microprocessor protective relay.
 
 
  4.5.3.1 Sync-check relay
 
 
    Sync-check relay, (ANSI Device 25). This relay will be capable of monitoring the voltage on the line and load side of the device. The protective relay will prevent closing the breaker unless the voltages levels are the same and the both systems are in phase.
 
 
  4.5.3.2 Voltage restrained overcurrent (ANSI Device 50/51V)
 
 
    This feature protects against generator overload and faults in the generator and the distribution system. If the voltage in the generator collapses during a fault the voltage restrained feature decreases the trip point value by seventy five percent.
 
 
  4.5.3.3 Ground overcurrent (ANSI Device 50/51G)
 
 
    This feature protects against ground faults in the generator and the distribution system.
 
 
  4.5.3.4 Differential overcurrent protection (ANSI Device 87)
 
 
    Current transformers (CT) monitor the currents entering and leaving the zone of protection and trips if the values differ more than the set point value. CTs are located on the load side of the synchronizing breaker and the neutral side of the alternator.
 
 
  4.5.3.5 Reverse power (ANSI Device 32)
 
 
    This device monitors the direction of power flow and will, after a time delay, initiate a trip when power flows from the distribution system to the generator.
 
 
  4.5.3.6 Over / under frequency protection (ANSI Device 81 O/U)
 
 
    This function trips if the generator frequency is outside the relay set point range of protection.
 
 
  4.5.3.7 Over under voltage protection (ANSI Device 27 / 59)
 
 
    This function trips if the generator voltage is outside the relay set point range of protection.
 
 
  4.5.3.8 Loss of excitation (ANSI Device 40)
 
 
    This function trips if the generator power factor is outside the relay set point range of protection.
 
 
  4.5.3.9 Volts / hertz protection (ANSI Device 24) and inadvertent generator energization (ANSI Device 50 / 27)
 
 
    These features provide off line protection features that protect against generator voltage regulator malfunction with the generator running but not synchronized to the utility.
5.
Possible Utility Power Requirements
 
IEEE 519-1992, 929-2000, 84 (Harmonic Limits and Voltage Fluctuations, Waveform)
Power Factor, Voltage, Frequency, Harmonic Distortion, Voltage Flicker, Waveform Distortion, Phase Imbalance Limitations
IEEE 1547 Standards for DC Injection, Immunity Protection, Surge Capability
6.
Island Mode
 
The installation of an on-site electric generating facility requires an interconnection agreement between the facility operator and the local electric utility before a generator can be connected with the electrical service. When electric power from the on-site facility is substantial enough, the interconnection facility and supporting agreement may enable the operator to function in “island mode,” delivering a number of significant advantages. Island mode involves removing a piece of equipment or the entire facility’s electrical load from the electrical grid and serving it directly from the engine-generator, with no interconnection or ability to take power from the electric utility. This is vital when the industrial facility or commercial/institutional operation cannot afford even momentary outages, or when it requires exceptionally high-quality electric power. Firms engaged in high-quality electro-plating, for example, may require an hour or more downtime before production can resume after a power outage of just a few seconds duration. For them, island operation represents insurance against unforeseen and expensive production downtime. At its most basic, island mode requires no interconnection equipment or switchgear to access the power grid. This is rarely a practical option, however, since power from the utility must be available when the engine generator is down for maintenance or when the facility’s load exceeds that produced by the generator. An improperly sized engine-generator, for example, may be unable to handle demand spikes caused by certain types of equipment such as motors that can draw three times their rated electrical demand during startup. While reliability and power quality are primary drivers in selecting a natural gas-fueled electric generating or CHP (Combined Heat & Power) installation, sufficient bottom-line savings may add to the appeal and reduce the payback time
7.
Black Start
 
Black start is the procedure for recovery from total or partial shutdown of electrical supplies throughout the country’s national transmission system or supplier distribution network. A little additional outlay on capital cost to ensure back-up for potential systems failure can prove to be a time and money-saving option. All power stations, with the possible exception of small hydro-electric generating stations, need an electrical supply to start up. To be able to black start, a station must have some form of independent auxiliary supply with sufficient capacity to supply the unit auxiliaries while a main generator is prepared for operation. This additional power source is usually provided by a smaller peripheral black start generating plant, which is started from a battery or other energy storage device. Once operational, the power plant can then be used to energize part of its local network, providing supplies for other plant within the area to enable them to start-up. For partial or total shutdown of the transmission system, the general principle of recovery includes re-establishment of isolated power stations to provide ‘power islands’; these are then integrated into larger sub-systems eventually allowing the re-instatement of the whole national grid system. By having this capability at a number of strategically located sites, electrical supplies can be rapidly restored. Back-up diesel or turbine sets for black starting the main generating plant used to be a common occurrence at power stations. The reasons for the lack of these facilities at most modern plants can be technical, but more often than not they are commercial - the extra capital costs for black starting can be prohibitive. Plant and grid failures are few but power companies and plant managers need to bear in mind that accidents and systems failures do occur. Without black starting, re-establishing the supply system can be difficult, severely delayed and therefore costly. Investing in a secure back-up is essential to minimize the consequences of system failure.
8.
Meeting Local Utility Standards
  Every local power utility has their own set of interconnection requirements which must be researched and met. While utilities are currently developing uniform standards to guide CHP interconnection (California rule 21 for example), facilities currently must design unique equipment scenarios for each plant. Major power utility requirements include grid connection, condition of power, switchgear and transformer access, and meter access.

Back To Top
 

Instrumentation

1.
Supervisory Control
  Evaluate existing control system for ability to expand and supervise new equipment packages. Data links may be established to new controls furnished with packaged system for data acquisition and supervisory set points.
 2.

Possible New Plant Steam Master for Brownfield Sites

  For plants with existing steam producing boilers, consider integrating the new HRSG into existing coordinated boiler control strategies. Coordination of some type will be required to allow the units to share steam loads without causing instability between the units.
    Option No. 1 – Expand existing controls to include new requirements including steam master and new balance of plant (BOP) auxiliaries
    Option No. 2 – Replace all plant controls if outdated
    Option No. 3 – Relatively few interconnect points required for coordinated control. Hardwire necessary interconnections.
    Option No. 4 – For coordinated control and more extensive data acquisition, investigate options and implement communication interface.
3.
Major Control Components
 
Major equipment is normally furnished with controls as part of the package including:
Burner Management (NFPA required compliance) if supplemental firing
Gas turbine and generator control
Gas Compressor (if required)
Chiller
HRSG, Chiller, and BOP equipment controls
Feed water control to HRSG
Management of Diverter (if equipped)
Supplemental firing rate of HRSG (if burner equipped)
Chiller start/stop operation
Chilled water set point and load management
Operation of various pumps, makeup water systems, cooling towers and other plant auxiliaries
Plant water chemistry measurement and control for cooling tower and boiler system
4.
Remote Monitoring
 5.
Safety
 
Gas Leak Detection Interrupt
Start building exhaust fans
Provide visual and audible alarms in building and at every entrance
6.
Emission and Environmental Monitoring 
 
CEM as required by local or federal regulation.
Blowdown monitoring as required by local authority
Blowdown monitoring as required by local authority

Back To Top
 

Mechanical Interconnections

Mechanical interfaces represent the bulk of the connections required with turbine generator-based CHP systems.
1.
Natural Gas
 
Turbine generators may operate on a variety of fuels: natural gas, diesel or distillate oil, landfill or waste gas, hybrid fuels, bio-fuel and high hydrocarbon fuel, are among the most prevalent.
 
 1.1
Natural Gas Specification
    Many CHP equipment manufactures provide a natural gas specification. Performance may only be guaranteed if the specification criteria are met. A gas analysis, usually obtained from the natural gas utility, should be compared with the specification. Additional equipment may be required to meet the utility’s gas specification requirements. For example, a pressure reducing station may be required to lower the gas pressure, and heaters may be required to remove any non-condensable particulate formed by this temperature drop and pressure reduction
 
1.2
Gas Compressors
    Turbine generator sets in the size range between 2 MW and 5 MW typically require medium to high pressure gas (175 psi to 325 psi) for operation. If proper gas pressure is not available locally, a new high pressure line(s) may be run from the gas utility. If this new gas line is cost prohibitive, gas compressor(s) may be installed. Redundant gas compressors and associated maintenance may be a costly item, and should be evaluated on a site by site basis. Multiple smaller gas turbine generator units which require lower gas pressure may indeed be a better investment in place of a new high pressure gas line or installing several gas compressors.
 
1.3
Leak Detection
    Many regulations, and good engineering practice, dictate that natural gas leak detection be utilized when working with high pressure gas systems. The leak detection system is typically tied in with the plant control system, and will automatically close the gas shut off valve in the event that gas is detected.
2. 
Diesel
 
 
Diesel and natural gas are by far the two most common fuels for turbine generator CHP systems. Higher emissions and diesel fuel cost usually prescribe natural gas as the fuel of choice, but diesel burning capability may allow a facility to leverage natural gas by buying from cheaper interruptible tariffs. A second fuel capability will further provide a solid back up fuel option incase a primary fuel is unavailable or not economical. On site diesel fuel will require storage tanks and any associated air/groundwater permitting. Secondary containment will been to be addressed if required, as well as the filing of any storm water pollution prevention plan (SWP3) or spill prevention control and countermeasure (SPCC) plans required by the regulator. Proper siting is required for filling access by the diesel supplier. Many turbine manufactures require an additional air compressor to start a turbine on diesel. 
3.
Chilled / Hot Water
 
The Broad USA unit converts hot gas exhaust from the gas turbine into chilled or hot water. The interface to these systems is typically a simple welded pipe connection. Hot tapping may be utilized to avoid interruption of an existing system. Additional control devices may be required if the new CHP equipment works alongside existing chilling and/or heating equipment. Chilled water systems will require cooling water systems, which include cooling towers, city water makeup, chemical treatment, blowdown, and freeze protection. Hot water systems also have simple chemical treatment.
4.
Steam
 
CHP equipment can often be integrated into an existing plant with no additional requirement for steam auxiliaries. Typical steam auxiliaries include condensate storage tanks, condensate return pumps, water treatment equipment, deaerator, blowdown and boiler feed pumps. If the CHP steam production is similar to the existing plant’s steam production, most of these auxiliaries may continue to be used.
5.
City Water
  Existing heating plants probably use city water for makeup, and treat the water with additional chemicals and equipment accordingly. Turbine compressor blades foul after a certain operational time, and require washing at regular intervals. Washing may be on-line or offline, and requires a specific water quality. Additional equipment may be required to remove impurities and/or hardness of the city water supply, and additional pumps may be required to increase water pressure.

Back To Top
 

Siting

1. Permiting
  Permits for construction and operation of a CHP facility will be required from federal, state, and local jurisdictions. The following list (adopted from Spiewak) represents a good starting point.
  1.1 Federal
   
Federal Aviation Administration Notification of Proposed Construction
NEPA Certification
U.S. Army Corps of Engineers Section 10 Permit
U.S. Army Corps of Engineers Section 404 Permit
U.S. EPA NPDES Permit
  1.2 State
   
Coastal zone management certificate of consistency
Cross connection permit
Environmental impact statement
Floodplain development
Gas pipeline approval
Groundwater discharge permit
Historical Commission approval
Industrial user discharge permit
Oil storage tank construction permit
PSD/air plans review
Sewer extension/connection permit
Siting approval
Solid waste facility operating permit
Solid waste facility site assignment
Surface water discharge permit (with NPDES)
Water quality certification
Water withdrawal permit
Wetlands approval of local order of conditions
  1.3 Local
   
Board of Health
Building Inspector
Conservation Commission
Department of Public Works
Fire Department
Historical Society
Planning Board
Water Department/Sewer Commission
Zoning Board of Appeals
2.

Utility Tie-ins

  Ideally, the the new CHP plant is close to the existing powerhouse, switchgear, site distribution systems, and fuel supply lines. This allows for easy integration with existing utilities. The turbine/generator set of the Reference Designs can be located next to the existing power plant in a weatherized enclosure.
3. Interior Siting
 
If the new CHP plant is integrated into an existing plant structure, the older structure may need to undergo a number of modifications including
Overcoming space limitations that may limit access to all components of the CHP plant
Upgrade of the existing chilled or hot water or steam piping
Upgrade of the existing power lines
Structural upgrades to accommodate the weight of the new equipment
Upgrade of the existing ventilation system
 
Independently if the CHP plant is located in an existing or a new building, at a minimum consideration should be given to the following.
Access to equipment
Fire code requirements
Maintenance access
Structural Consideration
Ventilation
Vibration isolation
4. Exterior Siting
 
Considerations with regard to the exterior siting of an CHP system are very similar to that of the interior siting. Of particular concern are:
Access to equipment
Aesthetics of the overall installation
Maintenance access
Noise
Soil &Structural Consideration
5. Noise
 
By their very design, combustion turbines are relatively quiet and vibration free. In general, they produce noise at high frequencies that easily can be attenuated. Following points may be considered to control the noise emissions of the CHP plant.
Attenuated turbine enclosure
Gas compressor noise suppression
Gas turbine exhaust stack muffler
Intake air attenuation
Plant wall soundproffing
Sound proof roll up doors and windows
Turbine enclosure ventilation

Back To Top
 

Utility Loads

Utility loads are patterns of usage of electrical and thermal energy requirements by the facility. They vary with the time of day and the seasons. The sucess of a CHP installation depends on the ability of the CHP plant to have all of its electrical and thermal output be continuously used by the facility, i.e., the CHP plant energy output profile should closely match the utility loads of the facility.

The CHP system is commonly used to baseload a facility’s thermal and electrical utility loads; small portions of utilities continue to be purchased through existing means. CHP may also be used to peak shave a facility’s electrical load; however total cycle performance decreases as heat recovery may not be fully utilized.

 1.

Electrical Demand/Usage

  A large portion of the cost-of-energy savings recovered by a CHP project is produced by generating electric power with the CHP equipment and offsetting electrical power normally purchased from the local utility. In some instances a CHP facility may be designed to also sell excess power to the utility grid. This, however, is rare in CHP facilities of this size.
  1.1 Site Load Control
    Site load control is normally accomplished by operating the generator equipment in parallel with the utility grid and the existing site distribution system.
  1.2 Electrical Generator Sizing
    The CHP electrical generator is normally sized to produce approximately enough electrical power to offset the minimum electrical demand that the facility consumes. A major focus on the initial CHP study is to determine the minimum electrical loading. This is often difficult to determine since most facilities record the maximum electrical demand and not the minimum. If the CHP electrical generation equipment is too large the facility will export power to the utility during minimum demand times. For the normal CHP facility of this magnitude this is usually not desirable.
  1.3 Utility Buy-Back
    CHP facilities can sell power to the utility. This may be to dispose of large amounts of excess power produced at low usage times or may be negotiated so that large variations in the steam distribution system can be managed without loosing the turbine. The reason that selling power to the utility is usually not feasible is due to the discrepancy between the utilities sell price and their purchase price. Normally what utilities are willing to pay for power will not offset the cost of operation for the CHP equipment.  
2.  Utility Tariffs
  Charges levied against the CHP are as varied as the number of utilities involved. To date there is no standard formula for determining the cost of utility charges so each case must be analyzed on its own merits. Charges from the utilities that may be anticipated are outlined below. 
  2.1  Cost of Utility Interconnection  
    Most utilities will expect the CHP budget to pay for the cost of inter connect. This usually will encompass the following. 
    2.1.1 Interconnect Study
      The first step in utility negotiations is to obtain a copy of their interconnect requirements. Some utilities require that an interconnect study be performed to set forth the specifications for the specific interconnect site. The cost of this study will be paid for by the CHP budget.
    2.1.2 Substation Cost
      If the site substation is owned by the utility, it is commonly expected that the substation be purchased from the utility.
    2.1.3 Metering Cost
      Since the average CHP site is not metered to accommodate cogeneration most utility interconnect agreements will include this charge.
    2.1.4 System Control and Data Acquisition (SCADA) Installation
      Some utilities require the installation of SCADA equipment. SCADA will definitely be required in those facilities selling power to the utility. If required, this installation will be paid by the CHP budget.
    2.1.5 Protective Relaying Improvements
      Cost of protective relaying improvements required to protect the cogeneration equipment will be paid by the CHP budget.
    2.1.6 Standby Charges
      Utilities will usually have some method or recouping the cost of standby power. Standby power is the power that is required when the CHP facility is down for maintenance or for the excess power purchased from the utility above that produced by the CHP. This tariff can be a negotiated firm demand with severe penalties for exceeding the negotiated amount, or it could also be a ratcheting demand where the facility pays a demand charge based on the largest demand set over the past twelve months. This charge is also different for each utility. 
  2.2 Other Charges
    Other charges to be expected is a service charge for each metering point, a cost of energy charge, a cost of demand charge 
    2.2.1  Demand Charges
      Demand charges are based on the largest demand measured in kilowatts or kilovolt-amperes required by the site during a fifteen-minute, or thirty-minute period of time depending on the utility.
    2.2.2 Power Factor
      A penalty for poor power factor or excess reactive power purchased is usually levied against the facility.
    2.2.3 Energy Charge
      A cost of energy charge for each kilowatt-hour consumed by the site will also be levied.
    2.2.4 Time of Day / Time of Year Charges
      These rates may differ for times of the year or even times of the day in which the energy is purchased. These billing rated are usually on peak and off peak with the on peak being the more expensive. For this reason maintenance on the CHP should be scheduled during off peak hours. Off peak hours are determined from the utility rate structure. 
3. Thermal Demand/Usage
  Turbine exhaust energy is converted or extracted through heat recovery equipment. 
  3.1  Steam
    Steam is probably the most common method of thermal energy produced by a CHP system. A heat recovery boiler is typically used to generate steam with the turbine exhaust. Supplemental gas may be consumed in a duct burner to increase the amount of steam generated. The upper limit of steam production is related to the amount of free oxygen (O2) in the turbine exhaust stream.
  3.2 Chilled/Hot Water
    Chilled water typically peaks in the warmer summer months, and hot water (if used primarily for heating) peaks in the winter months. A portion of hot water may be used year round for domestic purposes. The Broad USA unit is able to produce chilled water and hot water simultaneously, recovering energy in the turbine exhaust continuously.
  3.3 Process Heating
    There are a variety of process heating uses: drying operations, kilns, stripping, direct heating, etc. The exhaust ductwork may be directly tied into such a system, but typically requires a healthy bit of additional engineering effort. Care must be taken to not exceed the turbine manufacturer's exhaust static pressure limitation.
  3.4 Desiccant Dehumdification
    Recovered heat can also be used to regenerate an active desiccant systems. This may particularly be beneficial in facilities that require tight humidity control, are located in a hot and humid climate, or require high outdoor air intakes. Pretreating the outdoor air with actively regenerated desiccant systems can also reduce the required chiller capacity.

Back To Top
 

Waste

Several waste products are generated from a CHP facility, some of which require treatment before disposal through sanitary or storm sewers. Most facilities choose to use an off site disposal service in place of installing, operating, and maintaining waste treatment equipment.

Typical sources of waste requiring disposal may include:

  • Blowdown coolers
  • Gas compressors
  • Additives and chemicals used for treatment
  • Lube oil

Back To Top
 

Additional Information Resources

Codes & Standards 
  Building Codes
    First Source maintains detailed information on building codes for all 50 states, major cities, and some counties. The site offfers information on codes and amendments as well as contact information for up to 17 authorities having jurisdiction (AHJs) in each market.
    The International Code Council has developed a single set of comprehensive and coordinated national model construction codes. The ICC website offers information on which states and jurisdictions have adopted one or all of the international model codes.
  Mechanical Codes & Standards
    ANSI - American National Standards Institute
    ASHRAE - American Society of Heating, Refrigerating and Air-Conditioning Engineers
    ASME - American Society of Mechanical Engineers
    ASTM
    UL - Underwriters Laboratories
  Electrical Codes & Standards
    IEEE
    Pacific Gas & Electric -- This site provides information on Rule 21 generators
Online Journals
    Cogeneration and Competitive Power Journal
    Energy Engineering
Publications
    Alderfer, B.; Eldridge, M., Starrs, T., 2000. Making connections: Case studies of interconnection barriers and their impact on distributed power projects, National Renewable Energy Laboratory Report NREL/SR-200-28053.
    American Society of Heating, Refrigerating and Air-Conditioning Engineers, 2003. Handbook - HVAC Applications.
    American Society of Heating, Refrigerating and Air-Conditioning Engineers, 2000. Handbook - HVAC Systems and Equipment.
    American Society of Heating, Refrigerating and Air-Conditioning Engineers, 2003. Practical Guide to Noise and Vibration Control for HVAC Systems
   

Andrepont, J.S., 2001. Combustion Turbine Inlet Air Cooling (CTIAC): Benefits, Technology Options, and Applications for District Energy, Energy Engineering, Vol. 98, No. 3, pp52-69.

    Arthur D. Little, 1999. Distributed Generation: System Interfaces.
    Atkins, R.S., 2002. Environmental Permitting for Cogeneration and Merchant Power Plants, Cogeneration and Competitive Power Journal, Vol. 17, No. 1 (Winter 2001-2002), pp 54-70
    Bloomquist, R.G., F.S. Hazard, 2001. Integrating CHP into An Existing District Energy System A Cogeneration Case Study, Cogeneration and Competitive Power Journal, Vol. 16, No.1 (Winter 2000-2001), pp59-79.
    Chalifoux, A.T., B.L. Lynn, A.R. McNamee Jr., B.A. Deal, 1996. The Model Energy Installation Program: Progress and Lessons Learned, ASHRAE Transaction Vol 102, Pt. 2.
    Chambers, A., B. Schnoor, S. Hamilton, 2001. Distributed Generation: A Nontechnical Guide. Pennwell Corp.
    Czachorski, M., W. Ryan, J. Kelly, 2002. Building Load Profiles and Optimal CHP Systems, ASHRAE Transaction Vol 108, Pt. 2.
    ETSU 1999. Good practice guide 43: Introduction to large-scale combined heat and power
    Hamilton, S. 2003. Microturbine Generator Handbook, Pennwell Corp.
    Harrell, G., R. Jendrucko, 2003. Steam Turbine Versus Presuure Reducing Valve Operation, Cogeneration and Competitive Power Journal, Vol. 18, No. 2 (Spring 2003) pp25-36
    Lenssen, N. 2000. A Critical Technology: Interconnecting Distributed Generation to the Grid, Cogeneration and Competitive Power Journal, Vol. 15, No.3 (Summer 2000) pp. 18-25
    Maratan, A., P. Popovic, R. Radermacher, 2002. The Potential of CHP Technology in Commercial Buildings— Characterizing the CHP Demonstration Building, ASHRAE Transaction Vol 108, Pt. 1.
    Onsite Sycom Energy Corporation, 2000. The Market and Technical Potential for Combined Heat and Power in the Commercial/Institutional Sector, (Revision 1, January 2000) (PDF 359 KB) 
    Orlando, J.A., 1996. Cogeneration Design Guide, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc.
    Petchers, N., 2002. Combined Heating, Cooling & Power Handbook: Technologies & Applications, The Fairmont Press Inc.
    Spiewak, S., L. Weiss, L, 1997 .  Cogeneration & Small Power & Production Manual, Fifth Edition, The Fairmont Press Inc.
    The Chartered Institution of Building Service Engineers, 1999. CISBE Application Manual AM12, Small-scale combined heat and power for buildings. 
CHP Information Sources
    Combined Heat and Power (CHP) Program -- The Department of Energy's Office of Energy Efficiency and Renewable Energy is working on a number of fronts to support increased use of CHP technologies. This site provides information about the CHP Initiative, BCHP Initiative, Combustion Program, Steam Challenge Program, and the Federal Energy Management Program.
    DOE BCHP Initiative -- The objective of this site is to provide you with information on CHP systems to facilitate your decisions relating to these systems.
    EPA's CHP Partnership -- The CHP Partnership is a voluntary program that seeks to reduce the environmental impact of power generation by fostering the use of CHP. The Partnership works closely with the CHP industry, state and local governments, and other stakeholders to develop tools and services to support the development of new projects and promote their energy, environmental, and economic benefits.
    California Distributed Energy Resources Guide -- The California Distributed Energy Resources Guide is a public benefit site containing a wealth of information regarding distributed energy resources (DER).
    Midwest CHP Information Center -- The Midwest CHP Application Center was established in March 2001 for the U.S. Department of Energy (DOE) at the University of Illinois at Chicago (UIC) Energy Resources Center (ERC). The Center is a partnership between UIC/ERC and the Gas Technology Institute (GTI). Its mission is to provide application assistance, technology information, and educational support in the eight Midwest states of Illinois, Indiana, Iowa, Michigan, Minnesota, Missouri, Ohio, and Wisconsin.
    The Midwest Cogeneration Association (MCA) promotes a greater public understanding of cogeneration, independent power production, and distributed generation. In addition, MCA works to improve general business conditions of the industry. The non-profit organization provides pertinent information for its members to conduct research, publish reports, and hold various seminars and workshops with the goal to advance the concept of cogeneration throughout the Midwest
    The U.S. Combined Heat and Power Association (USCHPA) brings together diverse market interests to promote the growth of clean, efficient CHP in the United States. It is a private, non-profit association, formed in 1999 to promote the merits of CHP and achieve public policy support.
    California Alliance for Distributed Energy Resources (CADER) is a voluntary collaborative committed to facilitating the successful deployment of highly efficient and environmentally responsible distributed energy resources into competitive energy markets.
   

CHP -- This site gives you information about combined heat and power production (CHP) and district heating and cooling (DHC). The website provides you with information on combined heat and power (CHP) and district heating and cooling (DHC)from a technical, market and political point of view. The web site includes both general and country specific information about CHP and DHC in Europe.

    The Combined Heat and Power Association (of Great Britain) works to promote the wider use of combined heat and power and community heating
    Cogen Europe is the European Trade Association for the promotion of cogeneration. Its principal goal is to work towards the wider use of cogeneration in Europe for a sustainable energy future.
  Honeywell BCHP Project
  Honeywell
    Honeywell T.E.A.M. Services (for the Federal Government)
This site contains a link to the Ft. Bragg BCHP project.
    Honeywell Enterprise Building Integrator (EBI). This site prodes information the EBI technology, a scaleable system that pulls together all core building systems and integrates information from many different enterprise subsystems, including environmental controls.
  BCHP Team Members
    Broad USA -- Broad Air Conditioning is the world’s largest manufacturer of two-stage absorbers, selling approximately 500,000 tons of absorption cooling annually. Broad USA provided the absorption chiller for the project.
    Chelsea Group Ltd -- Chelsea Group. is a leading consultant to the indoor environment industry headquartered in Itasca, IL. With a specific focus on indoor air quality, Chelsea Group, provides strategic, technical, and marketing consulting to businesses that create products and provide services used to create resilient, productive indoor environments and to maximize asset value.
    I.C. Thomasson (ICT). ICT is a multidisciplinary engineering and consulting firm established in 1942 in Nashville, TN and currently has branch offices in Knoxville, TN, Tampa, FL, and an affiliated office in Brookhaven, MS. The company is licensed in 43 states and has completed more than 12,000 projects valued in excess of $18 billion. ICT provides engineering services to sports, medical, commercial, industrial, institutional, and military facilities throughout the United States and abroad.

Back To Top
 

CHPB HomeNews & EventsGeneral PublicTechnical ProfessionalsBuilding Owners
Policy MakersFinancial InstitutionsMarket SectorsSolicitationsLibrary Relevant Links

DOE DOE/DEDOE/EEREORNLRegional CHP Application Centers
Site MapContact UsDOE StaffDisclaimerComments

Last Revised: Friday, 26-Mar-2004 15:06:25 EST